EverWind says its planned artificial intelligence data centre in Cape Breton remains on schedule, with key agreements now in place and construction moving forward at its Point Tupper site near Port Hawkesbury, Nova Scotia.
Project Progress and Power Agreements
The company has committed $10 billion in private investment to the project. AI development firm Anthropic has signed a long-term lease to use the facility. Last week, EverWind also signed two separate agreements with Nova Scotia Power.
Stay connected to every major update — subscribe and follow us on the PhoenixQ website and across our social media platforms.
Brendan Chard, EverWind’s vice-president of power, says the company is taking steps to connect the data centre to the provincial electrical grid. He confirmed that EverWind will cover all incremental costs of service, ensuring existing customers bear none of the expenses related to powering the new facility.
The electric service contract covers the project’s first 95-megawatt phase. It also specifies that electricity will be provided on an interruptible basis. This means the grid operator can cut EverWind’s power supply with just 10 minutes’ notice during periods of grid pressure. In that event, the facility will switch to battery storage or a backup diesel generator.
EverWind ultimately plans to power the centre largely through its own proposed wind projects. However, those turbines will not be operational until 2028. As a result, the facility will depend on Nova Scotia Power’s grid during its first year of operation. Chard says the company is working to secure permits and maintain its target of going online in 2027.
Community Opposition and Power Consumption Concerns
Since the project’s announcement one month ago, protests have taken place across the province. Nick Tsergas, a science and technology journalist who founded StopTheDataCentre.ca, began his advocacy after a large data centre was proposed near his home in Hamilton, Ontario.
Tsergas says AI data centres consume significantly more power than traditional facilities. He estimates they use 10 to 20 times the electricity of a conventional data centre of the same size. Greater power consumption also generates more heat, requiring more sophisticated and resource-intensive cooling systems.
EverWind’s plan for Point Tupper includes a closed-loop cooling system. A water-glycol mixture circulates through a sealed loop rather than being routinely discharged. The company also notes that Nova Scotia’s cooler climate reduces cooling-water requirements for much of the year, with air used as the primary cooling method and water assistance reserved for the hottest periods.
However, Tsergas argues the full picture is more complex. He points out that backup diesel generators and gas turbines attached to data centres also require water for cooling. Therefore, overall water demand may be higher than initial descriptions suggest.
New Tariff Structure Required
Until a new fee structure is developed, EverWind will pay an interim large industrial tariff to access Nova Scotia’s grid. Nova Scotia Power says existing tariff structures were not designed for a customer of this scale. The utility added that its approach aligns with practices becoming common across North America.
EverWind says the data centre’s second phase could expand capacity to 420 megawatts. That phase is expected to complete in 2028, subject to regulatory approvals and conditions.